City of Barstow

Street Rehabilitation Project Map

Explore current and upcoming roadway improvement projects, affected streets, timelines, and status updates.

Interactive Map

Use the map below to view the project area. If the map does not load, the project details and street list are provided below.

Project Updates

Main Street Rehab
Status: In Construction
Affected Area: Main Street from 1st Avenue to 7th Avenue
Timeline: March 2026 - July 2026
Pavement rehabilitation, curb ramp improvements, striping, and traffic control updates.
Rimrock Road Improvements
Status: Upcoming
Affected Area: Rimrock Road from Avenue A to Mountain View Street
Timeline: Summer 2026
Roadway resurfacing and ADA access improvements scheduled for the next project phase.
Foglesong Area Access Work
Status: Planning
Affected Area: Local circulation routes near Foglesong Park
Timeline: To Be Determined
Pre-construction planning and access coordination for nearby improvements.

Legend

In Construction
Upcoming
Planning
Completed

Accessible Text Summary

This section provides a text-only summary of all active and upcoming roadway projects.

  • Main Street from 1st Avenue to 7th Avenue is currently under construction through July 2026.
  • Rimrock Road from Avenue A to Mountain View Street is scheduled for summer 2026.
  • Planning is underway for access coordination near Foglesong Park. Timeline is to be determined.